- Source: Conowingo Dam
The Conowingo Dam (also Conowingo Hydroelectric Plant, Conowingo Hydroelectric Station) is a large hydroelectric dam in the lower Susquehanna River near the town of Conowingo, Maryland. The medium-height, masonry gravity dam is one of the largest non-federal hydroelectric dams in the U.S., and the largest dam in the state of Maryland.
The dam sits about 9.9 miles (16 km) from the river mouth at the Chesapeake Bay, 5 miles (8 km) south of the Pennsylvania border and 45 miles (72 km) northeast of Baltimore, on the border between Cecil and Harford counties.
The dam supports a 9,000-acre reservoir, which today covers the original town of Conowingo. During dam construction, the town was moved to its present location about 1 mile (1.6 km) northeast of the dam's eastern end. The rising water also would have covered Conowingo Bridge, the original U.S. Route 1 crossing, so it was demolished in 1927. U.S. Route 1 now crosses over the top of the dam.
The Conowingo Reservoir, and the nearby Susquehanna State Park, provide many recreational opportunities.
Construction and hydroelectric power generation
The area, which appears on a 1612 map by John Smith, was originally known as Smyth's Falls.
On January 23, 1925, Philadelphia Electric Company awarded the construction contract for the dam to Stone & Webster of Boston, who did the design. Construction, which started in 1926, was carried out by the Arundel Corporation of Maryland. (Abandoned railroad tracks for transporting heavy equipment to the dam site can be seen along the western shore of the river below the dam.) When completed in 1928, it was the second-largest hydroelectric project by power output in the United States after Niagara Falls.
Some 5,000 workers flocked to this rural northeastern corner of Maryland, seeking to earn good pay as construction got underway. In addition to those working directly on the dam, large numbers relocated railroad tracks, paved new roads, and constructed steel towers to stretch the heavy transmission lines toward Philadelphia. This was nearly fifty years before Congress passed the Occupational Safety and Health Act, which guaranteed the right to a safe job. While these men struggled to earn a living, many suffered disabling injuries handling high voltage electric lines, tumbling from high elevations, managing explosives, encountering venomous snakes, etc.
When Maryland Public Television aired its documentary, "Conowingo Dam: Power on the Susquehanna" for Chesapeake Bay Week in April 2016, the question came up about how many workers died performing their duties. While investigating the death of Hunter H. Bettis on November 26, 1927, Darlington Coroner Wiliam B. Selse commented in The Baltimore Sun that more than twenty men had lost their lives. In an attempt to create a registry or census of job-related fatalities, death certificates, newspaper accounts, and funeral home books were examined. Fourteen individuals were identified.
The dam was built with 11 turbine sites, although only 7 turbines were initially installed, driving generators each rated for 36 megawatts. A turbine house, on the southwestern end of the dam, encloses these seven units. One additional "house" unit provides 25 Hz power for the dam's electric railroad system (identical to that used by the Pennsylvania Railroad, which had an electrified line [now under Norfolk Southern ownership] running on the eastern shore). In 1978, four higher-capacity turbines were added. Each of these turbines drives a 65-megawatt generator, increasing the dam's electrical output capacity from 252 to 548 megawatts. The four newer turbines are in the open air section at the northeast end of the powerhouse. The generators produce power at 13,800 volts. This is stepped up to 220,000 volts for transmission, primarily to the Philadelphia area. The dam contributed 2.1 million megawatt-hours to the electrical grid in 2021.
Through subsidiaries and mergers, the dam is now operated by the Susquehanna Electric Company, which is part of Constellation Energy. The current Federal Energy Regulatory Commission license for the dam was issued in 2021 and expires in 2071.
The Conowingo Hydroelectric Station would be a primary black start power source if the regional PJM power grid ever had a widespread emergency shutdown (blackout).
Flood control
The dam has 53 flood control gates, starting at the northeastern end of the powerhouse and spanning the majority of the dam. The floodgates are operated by three overhead cranes rated for 60 short tons (53.6 long tons; 54.4 t) each which were originally built by the Morgan Engineering Company of Ohio. The cranes run on rails the length of the dam and are electrically powered from lines that run above the face of the dam. A 4th crane was installed in 2006 at the powerhouse end of the rails, which required installing new power rails below the existing power wires. By 2017, all original overhead cranes had been replaced. The original Morgan cranes were removed and scrapped. The new cranes have backup generators installed on them to allow operation during a facility grid power failure.
In 1936, all the floodgates were opened for the first time. During Hurricane Agnes, in June 1972, all 53 floodgates were opened, for only the second time, and explosives planted to blow a section of the weir, as the waters rose during the early morning hours of June 24 within 5 feet (1.52 m) of topping the dam (a record crest of 111.5 ft (34.0 m), 3 feet (0.91 m) above normal level for the entire 14-mile (23 km) long Conowingo Reservoir.) Paul English, dam superintendent, released a bulletin at 10:30 p.m. on June 23 saying that the water levels were reaching a point at which the stability of the dam "cannot be controlled. When it reaches 111 feet (33.8 m)...it will be in the hazy area...It is not known...whether a structure of the dam may give and...people downstream should be advised." At this time, the flow sensor in the dam recorded its record discharge of 1,130,000 cu ft/s (32,000 m3/s), and the stream height gauge, at the dam's downstream side, registered a record 36.85 feet (11.23 m). On January 20, 1996, the gauge recorded its second-highest recorded crest of 34.18 feet (10.42 m). A severe ice jam also developed behind the dam on this date. The record minimum recorded discharge was on March 2, 1969, when the flow sensor registered 144 cu ft/s (4.1 m3/s).
On September 9, 2011, 44 flood gates were opened due to the impact of the remnants of Tropical Storm Lee. The Susquehanna River level behind the dam was 32.41 feet (9.88 m), the third-highest in history. The town of Port Deposit, located 5 miles southeast of the dam, was evacuated.
On July 26, 2018, 20 of the 53 floodgates were opened due to rising floodwaters resulting from several days of torrential downpours in the Mid-Atlantic. The Susquehanna River saw water levels of over 26.25 feet (8.00 m), placing nearby cities, like Port Deposit, at risk of flooding like in 2011. The ecological impact of this event is not known, but Chesapeake Bay ecologists are concerned about the health of the Chesapeake Bay with the influx of sediment and limiting nutrients, such as phosphorus and nitrogen, impacting water clarity and promoting algal blooms. The Coast Guard issued warnings for all vessels in the Chesapeake Bay regarding the fields of debris, floating and submerged, that had been released when the floodgates opened.
Ecology and environmental impacts
The river water impounded by the dam forms the 14-mile (23 km) long Conowingo Reservoir, known locally as Conowingo Lake. The reservoir is used as a drinking water supply for Baltimore and the Chester Water Authority; as cooling water for the Peach Bottom Nuclear Generating Station; and for recreational boating and fishing. In low rainfall or drought conditions, balancing the desire to maintain the reservoir level with the water flow needs for the downstream ecology is one of the challenges faced by the dam operators.
The Conowingo Dam, and to a lesser extent the Holtwood and Safe Harbor Dams farther upstream, stopped migratory fish species, especially American shad, from swimming further up the Susquehanna River to spawn. In 1984, a fish capture feature was added at Conowingo and shad were trucked upstream above all three dams and released. This program ended in 1999. A fish lift was installed in 1991. All three dams completed installation of fish lifts in time for the 2000 season. During the 2000 migration season, 153,000 American shad passed through the Conowingo fish lift. "However, passage rates of shad from Conowingo to Holtwood have been only 30 to 50 percent, suggesting that fish are having difficulty moving upstream in the waters of the Conowingo pool."
The three dams are also involved with another ecological concern. Normally, the reservoirs above each dam trap sediment and nutrients that run off from the Susquehanna River watershed and prevent some of that from reaching the Chesapeake Bay. A 1998 USGS study suggests that the reservoirs may reach capacity before 2020, and cease to reduce the nutrient and sediment load hitting the bay. However, the scouring of major floods, and other factors, affect this.
See also
List of dams and reservoirs of the Susquehanna River
List of power stations in Maryland
References
External links
Media related to Conowingo Dam at Wikimedia Commons
U.S. Geological Survey. Conowingo Dam real-time water flow data
Thinkquest (Oracle Education Foundation). "Conowingo Hydroelectric Plant." - Virtual tour with interior pictures and diagrams
National Weather Service. NWS Flood Stage Info. for Susquehanna River at Conowingo
Maryland Public Television. Promo Video: Conowingo Dam: Power on the Susquehanna [1] An introduction to the MPT one-hour documentary
Kata Kunci Pencarian:
- Sungai Susquehanna
- Conowingo Dam
- Conowingo
- Conowingo, Maryland
- Larry Hogan
- List of dams and reservoirs of the Susquehanna River
- Conowingo Bridge
- Port Deposit, Maryland
- U.S. Route 1
- U.S. Route 222
- Traction powerstation