    • Geodis Park, known during development and construction as Nashville SC Stadium and Nashville Fairgrounds Stadium, is a 30,109-seat soccer-specific stadium at the historic Nashville Fairgrounds in Nashville, Tennessee. It is the home of Major League Soccer club Nashville SC. The stadium opened on May 1, 2022, with Nashville SC hosting the Philadelphia Union in the stadium's inaugural match. The stadium will be one of twelve venues to host the 2025 FIFA Club World Cup.


      Construction


      In December 2016, the construction was expected to cost $275 million. Billionaire businessman John Ingram was expected to pay "$25 million up front and $9 million a year over 30 years to help retire Metro's annual $13 million debt for the $225 bond issuance." Additionally, the Nashville Fairgrounds would be renovated for an additional $40 million.
      As part of the public-private partnership, Mayor Megan Barry vowed to give "10 acres of city-owned fairgrounds land for a mix-use development next to the stadium" to the developers, including Ingram.
      The Metropolitan Council of Nashville and Davidson County approved $25 million in 2018, and an additional $5 million was approved directly by Mayor David Briley's office "from a 2017 contingency fund" without the council's approval in February 2019, for a total of $37.6 million.
      The stadium is part of a re-development project at the fairgrounds site that also includes a relocated Expo event space, new mixed-use retail and residential buildings and an upgraded Nashville Fairgrounds Speedway capable of hosting NASCAR Cup Series events.
      By February 2019, its construction had been delayed and its budget had increased. The original builder, Ely Concrete, abandoned the project and they were replaced by TRC Construction Services. By August 2019, the construction was expected to cost "between $325 million and $345 million", or "between $50 million and $70 million more than initial estimates," to be covered by billionaire Ingram and other investors, not taxpayers.
      As of July 2019, an exposition center was under construction for the State Fair. By August 23, the fair was expected to be held on September 6–15 "in the old fairgrounds space."
      A resolution to stop the demolition of buildings and make way for the stadium was introduced by council member Steve Glover on August 2, but it was voted down on August 21.
      Nashville SC was originally supposed to start playing in the stadium in 2020, but by 2019 it had been delayed to 2022.


      = Revised stadium deal and construction

      =
      On February 13, 2020, the agreements of the stadium deal were amended in order to allow for construction to begin on the site. This amended deal, an agreement reached by Nashville mayor John Cooper and the club's lead owner, John R. Ingram, stated that the team would fund 100 percent of the stadium's construction costs on the Fairgrounds site. This would be accomplished through lease payments on the stadium, cash investments, and revenue collected from the attendees of events at the stadium. In addition to the aforementioned agreement from the team, Nashville SC also committed to paying for the infrastructure in the immediate area around the stadium, estimated to cost $19 million. The team will pay $35 million in lease payments. Altogether, the team agreed to a total of $54 million in additional payments.
      In addition to the aforementioned monetary agreements of the deal, the team and the city came to an agreement on the parcel of land titled 8C which is about 2.4 acres in size and located between the stadium and the Fairgrounds Speedway. This parcel of land is what prohibited a deal from being reached prior to February 13, 2020. Mayor Cooper wanted the team to give up this piece of land and in a response to a letter from John Ingram, Cooper described parcel 8C saying, "The public space that links two 30,000-seat stadiums has the potential to become one of the most important in Nashville. Careful design and execution is essential to make the site work for two large public venues - supporting circulation, security, staging and access." Ultimately, the deal reached between the city and the team on February 13 stated that the piece of land would be made into a mixed-use open plaza that will allow space for future Fairgrounds and Speedway activities and uses.
      On March 16, 2020, demolition on the fairgrounds site began. On April 9, 2020, Ian Ayre published an open letter to fans stating that the demolition on the site is “progressing steadily and in a timely fashion." Ayre also stated that team had completed construction documents and that the expected completion date for the stadium is mid-May 2022.
      On March 10, 2022, a long-term sponsorship deal with Geodis, whose North American headquarters are based in nearby Brentwood, was announced, renaming the stadium to Geodis Park.


      Lawsuits


      In November 2017, Metro Nashville was sued by a group called Save Our Fairgrounds on the basis that the construction could disrupt the Tennessee State Fair, the Nashville Flea Market, and Fairgrounds Speedway racing activities. The lawsuit was dismissed by Chancellor Ellen Hobbs Lyle in December 2017. The dismissal was overturned by the Tennessee Court of Appeals in July 2019 to address the duties of the Fair Board and their ability to collect taxes on fairground activities.
      In January 2019, a second lawsuit was filed by Tennessee State Fair Association (TSFA), chaired by Republican Congressman John Rose, against the Metropolitan Government of Nashville and Davidson County. According to The Tennessean, the suit contended that the construction of the stadium failed to "leave sufficient space and structures for the state fair, which is a protected use in the Metro Charter." The suit was dismissed by the same judge, Ellen Hobbs Lyle, a few days later. The TSFA planned to take the case to the Tennessee Supreme Court, but on February 19, 2019, they decided to settle out of court and hope for a meeting with the Metropolitan Council.


      Design


      The stadium was designed by Populous, a firm in Kansas City that had also designed venues for other MLS clubs. The facility seats 30,000 people, making it the largest soccer-specific stadium in the United States or Canada. It includes six lounges, two dozen box suites, and a dedicated entry gate for the supporters group located on the north side.


      Transportation


      Geodis Park has 11 official parking lots around the Fairgrounds used for Nashville SC matches, which require a pre-paid pass. Several lots are paved, while others have gravel and grass surfaces; the stadium also has a ride-hailing lot. The WeGo Public Transit system has two bus stops near Geodis Park but does not run special late night services for matches.


      International matches




      = Men's matches

      =


      = Women's matches

      =


      Concerts and events


      Geodis Park also serves as a major concert venue.


      References




      External links



      Official website

    Kata Kunci Pencarian: