    • Neyveli Uttar pradesh Power Limited-Ghatampur Thermal Power Project is an upcoming coal-based thermal power plant located in Ghatampur in Kanpur district, Uttar Pradesh. The power plant is owned by the Neyveli Uttar Pradesh Power Limited a joint venture between Neyveli Lignite Corporation (51%) and Uttar Pradesh Rajya Vidyut Utpadan Nigam (49%).


      Status update


      Jan 2015: The land acquisition is completed.
      May 2015: South Pachwara Coal Block allotted to NLC India ltd for GTPS Project. MDO selection under progress
      Jun 2015: MoEF issued Environment Clearance on 17-Jun-2015
      Feb 2016: Centre to consider 1,980 MW Ghatampur project in Kanpur soon.
      July 2016: Centre approved for installation of Ghatampur Thermal Power Project (GTPC) of 1980 MW (3 X 660 MW) capacity through a joint venture company named "Neyveli Uttar Pradesh Power Limited (NUPPL)" formed jointly by Neyveli Lignite Corporation Limited (NLC) and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL).Untitled Page
      October 2016: Construction starts
      June 2021 inspection of railway line to power plant by railway DRM
      72Hrs continuous full load (660MW) Trial operation of Unit-1 is completed on 07-12-2024.
      Commercial operation of Unit-1 commences on 12-12-2024.


      Capacity


      The planned capacity of the power plant in 1980 MW. The power plant is secured with coal supply.

      The plant has a power purchase agreement (PPA) with Uttar Pradesh Power Corporation (UP Power Corporation) and Assam:
      Uttar Pradesh Power Corporation: The plant will supply 75.12% of its power to UP Power Corporation.
      Assam: The plant will supply 24.88% of its power to Assam.