• Source: Patrind Hydropower Plant
  • Patrind Hydropower Plant is a run-of-the-river, high head project of 110 metres (360 ft), located on Kunhar River near Patrind Village of Mansehra District, right on the border of Abbottabad District of Khyber Pakhtunkhwa Province and Muzaffarabad city of Azad Kashmir, Pakistan. It is approximately 138 kilometres (86 mi) from Rawalpindi and Islamabad and about 76 kilometres (47 mi) from Abbottabad city.
    The dam and the tunnel has been constructed on Kunhar River at Patrind Village in Muzaffarabad District, AJK and Abbottabad District on the right bank in Boi Village and the power house on the right bank of Jehlum River in Muzaffarabad, AJK at lower Chattar near Thuri Park.


    Design and construction


    The Korean construction company Star Hydro Power Limited (SHPL), an Independent Power Producer (IPP), has set up the 150 megawatts (200,000 hp) Patrind Hydropower Plant, which is the second private hydro power project in Pakistan. Project is being financed by IFC, ADB and K-Exim Bank. The company has completed the project in a period of three-and-a-half years at an estimated cost of $400 million. The project would generate 150 megawatts of electricity which would not only help improve the electricity voltage in Abbottabad and Mansehra districts but also boost economic activities in the region.
    Since the project is being developed by SHPL as an IPP, the SHPL has entered into a 30-year Power Purchase Agreement with National Transmission and Dispatch Company (NTDC), Pakistan's grid system operator, for the sale of electricity generated from the Project.
    The first independent hydro power project in the private sector – New Bong Escape Hydropower Project of 84MW – has already been completed and started commercial operation in March 2013.
    The total electricity generation capacity of the Patrind Hydropower Plant is 150 MW. A surface type powerhouse to accommodate three Vertical Francis Turbine Units, each of 50 MW capacity, is proposed on the right bank of Jehlum River. The powerhouse site is about 8.52 kilometres (5.29 mi) upstream of the Kunhar – Jhelum confluence. The crest elevation is 757 m which is approximately 26m high from the river bed. There will be four radial type crest gates each 13 by 10 metres (43 ft × 33 ft) in size.


    See also



    List of dams and reservoirs in Pakistan
    List of power stations in Pakistan
    Khan Khwar Hydropower Project
    Satpara Dam
    Gomal Zam Dam
    Duber Khwar hydropower project
    Kohala Hydropower Project


    References

Kata Kunci Pencarian: