- Source: Seaton Delaval railway station
Seaton Delaval is a railway station on the Northumberland Line, which is due to reopen in the summer of 2024, and will run between Newcastle and Ashington. The station will serve the villages of Seaton Delaval and Seghill in Northumberland, England.
History
The station was opened on 28 August 1841 by the Blyth, Seghill and Percy Main Railway, a predecessor of the Blyth and Tyne Railway. The station was situated on the south side of the Station Road (A192) bridge. After the footbridge subsided in 1940 due to a wartime barricade, all of the trains used the down platform. The principal goods traffic was bricks; this ceased in 1963. The station was closed to passengers on 2 November 1964, and closed completely on 7 June 1965.
= Reopening proposals
=Proposals to reintroduce passenger rail services to the currently freight-only section of the former Blyth and Tyne Railway system have been discussed since the 1990s.
In the early 2010s, Northumberland County Council became interested in the proposals, commissioning Network Rail to complete a GRIP 1 study to examine the best options for the scheme in June 2013. This report was published in March 2014 and was followed in June 2015 with the commissioning of a more detailed GRIP 2 study at a cost of £850,000. The GRIP 2 study, published in October 2016, confirmed that the reintroduction of a frequent seven-day a week passenger service between Newcastle, Ashington and possibly a new terminus to the east, at Woodhorn, was feasible and could provide economic benefits of £70 million with more than 380,000 people using the line each year by 2034. The study suggested that due to the short distance between the former stations at Seaton Delaval and Seghill only one, rather than both, should be reopened.
Despite a change in the political leadership of Northumberland County Council following the 2017 local elections the authority continued to develop the project, encouraged by the Department for Transport's November 2017 report, A Strategic Vision for Rail, which named the line as a possible candidate for a future reintroduction of passenger services. Consequentially, NCC commissioned a further interim study in November 2017 (dubbed GRIP 2B) to determine whether high costs and long timescales identified in the GRIP 2 Study could be reduced by reducing the initial scope of the project, but the report failed to deliver on this.
Nonetheless, the county council has continued to develop the project, hiring AECOM and SCL Rail as contractors to develop the scheme on their behalf in 2018 and allocating an additional £3.46 million in funding for a further business case and detailed design study (equivalent to GRIP 3) in February 2019. Revised plans were revealed in July 2019 which were reduced in scope from the 2016 GRIP 2 study and proposed 4-phase project to reduce the initial cost of the scheme. The revised plans appear to suggest that Seaton Delaval, rather than Seghill, had been selected for reopening but, even on its own, Seaton Delaval was to be excluded from the initial £90 million phase and was only to be reopened during Phase 2 of the project. In Phase 4 it was proposed to add a passing loop in the vicinity of the station to enable the introduction of a half-hourly passenger train service. However, in August 2020, it was reported that these four proposed phases might be merged into a single one.
The North East Joint Transport Committee's bid for £377 million of funding from the UK Government's £1.28 billion Transforming Cities Fund, submitted on 20 June 2019, includes £99 million to fund the reintroduction of passenger services between Newcastle and Ashington, while further work is ongoing to secure additional public and private investment for the project.
The Department for Transport allocated an initial grant of £1.5 million towards the project costs in January 2020 which was supplemented by an allocation of £10 million of funds from Northumberland County Council the following month. This funding enabled AECOM to begin detailed on-site ground investigation works in October 2020. The allocation of a further £34 million of UK Government funding for the project in January 2021 enables the necessary land to be purchased, detailed designs to be prepared and some early preparatory and site works to begin. In January 2021, it was anticipated that the UK Government would fund the remainder of the project cost, estimated at £166 million as of January 2021, once the final phase of design works were completed. However, in April 2021, it was reported that government officials were seeking to reduce the cost of the project as part of the Department for Transport's Project SPEED initiative. It was reported that the cost-saving measures under consideration included and cutting initial service frequencies from two to one trains per hour and dropping the proposed Blyth Bebside station from initial project scope (although the latter option was later publicly ruled out by Minister for Railways Chris Heaton-Harris).
A planning application for the proposed new station at Seaton Delaval was submitted to Northumberland County Council on 3 June 2021. The submitted planning documents indicate that the new station will have a single 100 m (110 yd) platform, located on the southeastern side of the remaining single line a short distance to the southwest of the site of the previous station's platforms. The station will be served by a new 284 space car park, accessed via a dedicated access road off of the A192 road, as well as a new segregated cycleway and footpaths.
Northumberland County Council submitted a Transport and Works Act Order application to the Secretary of State for Transport Grant Shapps on 26 May 2021, under which they would be conferred certain additional powers deemed necessary for the new stations to be constructed and the line upgraded to carry regular passenger services. If approved, the new Seaton Delaval station will be constructed by the project's primary construction contractor, Morgan Sindall. It was anticipated that the main construction phase could begin in early 2022, enabling an opening date in 2024.
Construction of the new station is underway and is expected to be ready in time for the line opening in summer 2024.
Services
Weekday and Saturday daytime services are expected to operate twice-hourly, with an hourly service during the evening and on Sunday, with an end-to-end journey time between Newcastle and Ashington of around 35 minutes. All services are expected to be operated by Northern Trains.
(Expected) rolling stock used: Class 156 Super Sprinter and Class 158 Express Sprinter
References
= Sources
=Bevan, Alan, ed. (1998). A-Z of Rail Reopenings (fourth ed.). Fareham: Railway Development Society Ltd. p. 59. ISBN 0-901283-13-4.
"Connecting Communities – Expanding Access to the Rail Network" (PDF). London: Association of Train Operating Companies. June 2009. Retrieved 7 September 2018.
"21/02253/CCD - Planning Application Documents". Northumberland County Council. 3 June 2021. Retrieved 30 June 2021.
External links
Kata Kunci Pencarian:
- Seaton Delaval railway station
- Seaton Delaval
- Seaton railway station
- Seaton
- Seaton Sluice
- Blyth and Tyne Railway
- Seghill railway station
- New Hartley
- Newcastle railway station
- Seahouses railway station